MSP 5.1 Assigning Work Resources to Tasks

Assigning Work Resources to Tasks

MSP 2010

This includes:

1-Entering Resources on Task Information Tab

2-Entering Resources in Detail View

3-Adding Assignment Units

 

Work Resources entered in the Resource Sheet now need to be assigned to Individual Tasks. Both People and Equipment Resources are entered in the same way. They can either be entered through the Task Information Tab or in the Detail View.
Once the Resources are assigned, their Units (that is how much they will work, e.g. half day / full day, etc.) can be set for individual resources. As we have already entered the costs for the resources, the cost for each resource for that particular task gets calculated based on the assignment units and duration of the task.