After we have assigned resources to tasks, we can also add additional resources. Additional Resources are added in the same way as shown earlier in the resources sheet. These affect the task duration for all Effort Driven Scheduling.
Task Duration decreases with increase of Additional Resources. i.e. If a work was done by a resource in 2 days, adding an additional resource to the task will make the duration of the task 1 day.